| joints are grouted |
Saturday, February 23, 2013
Grout
After a short delay, the tiles are grouted. Now just awaiting a final cleaning then return to the walls and ceiling to finish mudding the seams.
Wednesday, February 20, 2013
A full day of taping
All those ugly gaps are gone and sealed up with the first coat of joint compound. I found a nice new tape that works very well in the corners and spans some the wider gaps. Ireally do hate to tape as it a skill I have not mastered but lots of sanding and some flat paint should take care of any imperfections.
Also finished the frame for the bumpout. The reason it has to jog back towards the wall is because it would run into the window if we maintained the 12" shelf.
Time for some rest - so back to real work for a few days then we'll see what develops over the weekend.
| corners are taped |
![]() |
| opposite corner taped |
![]() |
| lights are up temporarily |
| Bump out built and ready for beadboard |
![]() |
| looking in from the dining room |
![]() |
| this how the beadboard will go around the bend |
Tuesday, February 19, 2013
Sheetrock
| positioned just right |
![]() |
| the wheel has a brake to keep it from coming down - a very simple way to push that rock to the ceiling. |
Here's a little better look of the sheetrock lift. It's holding up the final sheet of ceiling rock - yay! It's very adjustable but the wide legs make for a tight fit on an 8' by 20' room.
| I got the cutouts for the outlets right the first time - miracles do happen occaisionally! |
![]() |
| this bump out is for a shelf and to hold a bookcase |
Monday, February 18, 2013
Heavy lifting
| faired out wall |
| first sheet of wallboard |
![]() |
| ceiling is underway |
Sunday, January 27, 2013
Perimeter tiles installed
An afternoon of cutting to fit filled in the remaining gaps on the floor. Next step will be grouting. That step is the subject of some discussion. Current thinking is to tile the sides and top it with some boards that were taken up from the previous porch floor or to use some of the wide boards we saved from the second story project. Stay tuned. Once the floor is done the ceiling will go up and the walls will get wainscotting and drywall.
Floor Tiles
Tiling has begun. We're using 18"x18" ceramic/porcelain tiles in a grid pattern. We've started out with the full size tiles then will follow with the cut tiles around the perimeter. The round orange pieces are the spacers - 1/4"for the grout. The white pieces go under two adjacent tiles and when the wedge is inserted, bring them to the same level (making up for some of the imperfections). The heating is working well as we've seen single digit temperatures for most of the week while the room remains in the 60's.
| levelers and spacers |
Monday, January 21, 2013
Restarting the project!
Well, we're back after a long absence. A New Year's resolution to finally button up the porch project along with many visits from friends and family and the universal comment "you still haven't finished?" has been the kick in the butt we've needed to get to action.
First step is to get the floor tiled. To do that we have to install the heating elements - in our case a Honeywell system that is electric. In the picture below you can make out the coils that go back and forth. These were set in a mortar. Since it is winter and the slab is very cold, we made the connections and turned it on in order to help cure the mortar.
![]() |
| First layer - heating elements |
![]() |
| Powered up and registering 61 degrees! |
The next step is to provide a separation layer between concrete of the base slab and the final surface tile. In order to do that effectively we've used a great new product from Germany. It is essentially a hybrid of fabric attached to a plastic. The fabric is mortared onto the slab then another layer of mortor is placed on top filling the blocks. The system allows for differential movement reducing (hopefully eliminating) any chance for cracking.
| Separation layer |
![]() |
| Ready for tile! |